Yan Yean to Bald Hill Pipeline
The pipeline spans 20 kilometres, connecting the Yan Yean Water Treatment Plant to the Bald Hill Tank in Kalkallo. Its development aimed to enhance supply reliability in the northern suburbs and create additional transfer capacity to the west. Construction activities commenced in early 2023 and concluded in early 2025.
A pumping station at Yan Yean Reservoir pushes water into the pipeline. The tank, 10 metres tall and 36 metres’ diameter, receives and stores the water, then pumps it to nearby communities via the Yarra Valley Water network.
A notable feature of this project was its focus on bulk water transfer, precluding any property connections along the pipeline’s alignment. This restriction underscored the critical nature of this infrastructure, primarily designed to augment water distribution and cater to the evolving needs of Melbourne’s expanding population.
Integral to the pipeline’s delivery was Touch Projects’ expertise in scheduling and project coordination. Our role required meticulous timeline planning, resource allocation and task sequencing to ensure optimal efficient construction. This high-value project is one of nine for which Touch Projects is providing services, as part of a Melbourne Water portfolio of infrastructure upgrades.
In undertaking scheduling, Touch Projects coordinated the intricate web of tasks for the pipeline’s successful delivery, from procurement and construction through to quality assurance and compliance. The technical complexities of laying a 20-kilometre pipeline requires synchronisation of various construction phases, including trenching, pipe laying, welding and testing. Moreover, seamless coordination with stakeholders, such as internal teams, contractors, engineers and inspectors, was essential to ensure that scheduling objectives were met.
Our role also encompassed risk assessment and mitigation. Potential challenges such as geological issues, adverse weather and regulatory approvals, required a proactive approach. The utilisation of scheduling and project management software was instrumental in the continuous monitoring and adjustment of project timelines to accommodate unforeseen contingencies.
Sector
Water
Client
Melbourne Water
Project Value
$108.7 million